Dear Editor,
I would like to bring in your notice that work on Mastuj bridge and
road is in progress @ the speed of tortoise. This has badly
suffered life of people of the area from Booni to Shandoor and
Broghil.
For your reference we would like to mention just one example of bus
fare and transportation charges from Chitral to proper Mastuj.
Total distance from Mastuj to Chitral is 107 kilometer. Out of 107
km Booni to Mastuj only 33 km is rough road. This time transporters
are charging Rs.200 from Chitral to Mastuj and Rs. 100 from Booni
to Mastuj per passenger. Rs.100 per 40 kilogram for transportation.
Now it is beyond control of public how bear these heavy charges.
Indicators of poor speed work at bridge and road
1 Limited number of human resources at bridge work
2 Very rare use of machines
3 Only one machine is working on road
4 Absenteeism of labors very common at bridge and road work
5 The existing machines are too old and developing fault
frequently.
Therefore, through your esteemed online we request to Govt:
high-ups to speed up the construction work on Booni Shandur road
and Mastuj bridge.
With best regards
Ibrahim Qabool
Chitral
|